Tee Complex Contruction:
- Spray 2 Applications of Round-up to prevent TifSport contamination in the new Celebration Bermudagrass. These applications will be made over the next few weeks prior to the construction work. The treated tees will be visibly "Blue" from the application and begin turning brown over the next 4-5 days.
- DST Sports Turf Construction will cut & remove the existing TifSport from the above mentioned tees.
- Roto-till the tee surfaces to prepare for Laser Leveling.
- Laser Level the tee surfaces to +/- 1/4".
- Sod the tee with Celebration Sod.
#18 Tee Before Construction
Step 1: Spraying to remove the existing TifSport on #2 Tee
Step 1 Complete: #11 Tee
The final product will be a level and consistent teeing surface. As each phase is completed we will update on the progress and what to expect on the course.